Stabilization Overview
The Redevelopment Authority is actively engaged in stabilizing the Courthouse property. Listed below are periodic updates on these efforts.
1820 Courthouse Update Notices
NoticeUpdate Date
The Roof contract is approximately 70% complete., the ornaments &  balustrades have been moved off site for repair & painting.

Decorations are brought to you by Plymouth Redevelopment Authority, Board members, staff & 1820 Consortium members.
12/2/2010 
The asbestos removal is completed. On 9/22, Meadows Construction began work on the roof and cupola. Work is expected to take 2-3 months depending on the weather. 9/22/2010 
The asbestos abatement continues and will take approximately 2 more weeks. The contractor is reaching the final stage, which encompasses abatement of all the crawl-spaces. The contract for the roof and cupola have been awarded to Meadows Construction Co., LLC. Work will commence once the contract and documents are executed. 8/31/2010 
On August 9, 2010, the contract for asbestos removal will begin and take approximately 3 weeks. The contract was awarded to TMC Service, Inc. under a competitive bid. R.I. Analytical is the project engineer/monitor. During the project, containers with asbestos will be stored on site in front of the Courthouse. These are safe and meet all containment requirements. 8/1/2010